Spot-Fixing Scandal
BCCI chief's son-in-law arrested
Mumbai Police apprehended Gurunath Meiyappan, a key official of the Indian Premier League's (IPL) Chennai franchise, late on Friday in connection with a spot-fixing scandal that has also led to the arrest of three cricketers. Full Article
REUTERS SHOWCASE
Deflated expectations
Breakingviews columnists discuss the implications of inflation being in decline globally. Video
Revenge of Markets
For months, markets have been dancing to central bankers' tune, but that may now be changing, writes James Saft. Full Article
Buy, Sell or Hold?
Confused while buying stocks? Get buy, sell or hold recommendations from VantageTrade. Full Coverage
Reuters India Mobile
Get the latest news on the go. Visit Reuters India on your mobile device. Full Coverage
Trans Alaska Pipeline to halt for maintenance
ANCHORAGE, Alaska, July 26 (Reuters) - The Trans Alaska Pipeline will shut
down over the weekend to allow scheduled maintenance work, a company spokeswoman
said on Thursday.
The shutdown is scheduled for Saturday and expected to last for 18 hours,
said Michelle Egan, corporate communications director for Alyeska Pipeline
Service Co, the pipeline's operator.
North Slope oil output will be curtailed during the shutdown, with the
cutbacks spread among the producers, Egan said.
"We are coordinating a pro-ration with the producers, so there'll be a
slowdown in production for the 18-hour period," she said.
Throughput in the pipeline averaged 517,573 barrels per day in June and
582,353 barrels per day for the first half of 2012, Alyeska reported.
The focus of this weekend's shutdown -- the fourth of the summer -- is
mainline valve testing. A final summer maintenance shutdown is set for Aug. 5,
Egan said.
In the past, Alyeska has conducted one or two shutdowns each summer to allow
for major projects to be completed without oil-flow complications. Those
shutdowns typically lasted 36 hours.
This year, the company has opted for more frequent shutdowns of shorter
duration, Egan said. Alyeska has been using temporary bypass lines that allow
for maintenance tasks to continue even after throughput resumes, she said.
Meanwhile, Alyeska's corporate ownership is undergoing a change.
As of Aug. 1, minority owners Chevron and Koch Industries will no
longer be shipping any oil through the system. The two companies account for
just under 4.5 percent of Alyeska's ownership.
Earlier this summer, the companies gave notice to Alyeska's major owners -
BP, ConocoPhillips and Exxon Mobil - that they were
withdrawing from the Trans Alaska Pipeline System consortium.
The major owners will decide what to do with the Chevron and Koch shares,
Egan said.