April 26, 2018 / 8:43 AM / 5 months ago

FACTBOX-China refinery maintenance outages in Spring/Summer 2018

    BEIJING, April 26 (Reuters) - Some of the China's largest refineries, including Sinopec's
Zhenhua Refining and Chemical Company, will shut for maintenance starting in the second
quarter. 
    The table below shows maintenance plans for 11 refineries in the second and third quarter. 
    Data in the factbox were compiled from a survey of market sources and company statements. 
    
 Company    Location           Processing       Maintenance Period                             
                               Capacity ( in                                   
                               million tonnes)                                 
 Sinopec    Tahe                             5  March 25 to May 6              Full shutdown 
            Shanghai Gaoqiao                13  Starting March 20 for 69 days  Full shutdown 
            Anqing                         5.5  From March 20 to April 30      Some refining
                                                                               and chemical
                                                                               unit 
            Zhenhai                         23  Starting May for 40 days                       
 CNPC       Jilin                           10  Starting end of April for 20   Full shutdown 
                                                days                           
            Wepec in Dalian                 10  From mid April for 20 days     Maintenance of
                                                                               desulphurization
                                                                               unit 
            Sichuan                         10  Starting April 8 for 60 days   Full shutdown 
 CNOOC      Huizhou                         12  Starting October for 60 days   Full shutdown 
 Private    Tianhong Chemical                5  Starting April for 30 days     Full shutdown 
            Shandong Haike                 2.2  Starting June for 30 days      Full shutdown 
            Group                                                              
            Shandong Haiyou                3.5  Starting April 11 for about 1  Full shutdown 
            Petrochemical                       month                          
            Group Co                                                           
 Total                                    99.2                                                 
 Capacity                                                                      
    

 (Reporting by Meng Meng and Aizhu Chen; Editing by Tom Hogue)
  
0 : 0
  • narrow-browser-and-phone
  • medium-browser-and-portrait-tablet
  • landscape-tablet
  • medium-wide-browser
  • wide-browser-and-larger
  • medium-browser-and-landscape-tablet
  • medium-wide-browser-and-larger
  • above-phone
  • portrait-tablet-and-above
  • above-portrait-tablet
  • landscape-tablet-and-above
  • landscape-tablet-and-medium-wide-browser
  • portrait-tablet-and-below
  • landscape-tablet-and-below